Hey everyone, 


We know you've been waiting for news over this so here is the status of the boards: 


These PCBs should have been done by the end of last month. Currently, our PCBA factory has 80% of the components and empty boards. They are still waiting for us to send the rest of components. 


Unfortunately, we need some more time to buy these components. After they receive all components, they can finish all the boards up in 25 working days. The boards will be finished in one shot.  


As mentioned, due to the nature of crowdfunding and production costs associated with these campaigns, much of our cash flow to finish these projects comes from our parent company, Light Harmonic. Light Harmonic pushes cash flow to LH Labs whenever possible. 


At this point, we have no exact date on when the rest of the boards will be completed, but we are working on obtaining funding to complete the campaign. We'll update you whenever possible over developments. 


The entire LHL team